D3 motorway (Slovakia)

The Motorway D3 (formerly D18), sometimes called the Kysuce Motorway, is a motorway in northern Slovakia. Initially, it is supposed to be only a two-lane motorway in the Svrčinovec - Slovak/Polish border section, and four-lane motorway in the remaining Hričovské Podhradie - Čadca section.It lies on these E-roads: E50, E75 and E442.

D3 Motorway shield}}
D3 Motorway
Diaľnica D3
     Completed        Under construction        Planned
Route information
Part of E75
Length34.8 km (21.6 mi)
Under construction: 5.7 km (3.5 mi)
Planned: 60.8 km (37.8 mi)
Major junctions
From D1 near Hričovské Podhradie
Major intersections R5 near Svrčinovec (planned)
To S1 border with Poland
Location
CountrySlovakia
RegionsŽilina Region
Major citiesŽilina, Čadca
Highway system
D2 D4

It starts at the motorway junction with the D1, bypassing Žilina, then goes to the north around Kysucké Nové Mesto and Čadca, having an interchange with the R5, and ends near the village of Skalité, where it crosses the Polish border and connects to Expressway S1.This is one of the most important motorways in Slovakia and an e-vignette is required to use this motorway. The whole motorway has 2 lanes on each side.

Sections of the motorway

Section orderSection designationSection length in kmStart of construction

section

Introduction of section to

operations

Exits and intersections
1.Hričovské Podhradie – Žilina, Strážov6.9200520081. Crossroad D3xD1, Hričovské Podhradie

2. Žilina, Strážov

2.Žilina, Strážov – Žilina, Brodno4.3201420173. Žilina, Brodno
3.Žilina, Brodno – Kysucké Nové Mesto11.2202520284. Kysucké Nové Mesto
4.Kysucké Nové Mesto – Oščadnica10.8202420275. Beautiful above Kysuca
5.Oščadnica – Čadca, Bukov4.8Left half, 1996Left half, 2004901. Temporary connection to road I/11
5.Oščadnica – Čadca, Bukov4.8The right half

2024

The right half

2027

section without exits
6.Čadca, Bukov – Svrčinovec5,7201620206. Čadca, Bukov

7. Čadca, Podzávoz

7.Svrčinovec – Skalite12.3Right half, 2013Right half, 20178. Svrčinovec
7.Svrčinovec – Skalite12.3Left half, after 2040Left half, after 20408. Construction of the intersection D3xR5, Svrčinovec instead of the Svrčinovec exit
8.Skalité - state border SK/PL3.1Right half, 1997Right half, 20179. Skalite
8.Skalité - state border SK/PL3.1Left half, after 2040Left half, after 20409. Skalite

-

See also


🔥 Top keywords: Main PageSpecial:SearchPage 3Wikipedia:Featured picturesHouse of the DragonUEFA Euro 2024Bryson DeChambeauJuneteenthInside Out 2Eid al-AdhaCleopatraDeaths in 2024Merrily We Roll Along (musical)Jonathan GroffJude Bellingham.xxx77th Tony AwardsBridgertonGary PlauchéKylian MbappéDaniel RadcliffeUEFA European Championship2024 ICC Men's T20 World CupUnit 731The Boys (TV series)Rory McIlroyN'Golo KantéUEFA Euro 2020YouTubeRomelu LukakuOpinion polling for the 2024 United Kingdom general electionThe Boys season 4Romania national football teamNicola CoughlanStereophonic (play)Gene WilderErin DarkeAntoine GriezmannProject 2025